Section 11.97.330. Amendment of reclamation plan.  


Latest version.
  • 	(a)  A miner shall ensure that reclamation work complies with an approved reclamation plan. If changing product prices, economics, financing, unanticipated conditions, or suspension of mining operations necessitates a change in the reclamation plan, the miner shall submit an amended reclamation plan for approval before modifying the approved reclamation work.  
    	(b)  If new or changed statutory or regulatory requirements affect reclamation under an approved reclamation plan, the miner must submit an amended reclamation plan for approval to demonstrate that reclamation occurring after the effective date of the new requirements will comply with those new requirements.  
    

Authorities

27.19.030;27.19.070;27.19.100

Notes


Reference

11 AAC 97.350
Authority
Sec. 2, ch. 92, SLA 1990 AS 27.19.030 AS 27.19.070 AS 27.19.100
History
Eff. 7/30/92, Register 123