Section 12.21.080. Changing from specialty or mechanical contractor to general contractor.  


Latest version.
  • A registered specialty or mechanical contractor that is changing to a general contractor must apply for the change in registration under this section. The contractor must submit  
    		(1) a complete application, on a form provided by the department;  
    		(2) the applicable fees established in 12 AAC 02.180;  
    		(3) either a new surety bond or an endorsement to the surety bond on file with the department, as required by AS 08.18.071;  
    		(4) evidence of current public liability and property damage insurance, as required under AS 08.18.101;  
    		(5) if applicable, workers' compensation insurance as required under AS 08.18.101.   
    

Authorities

08.01.080;08.18.021;08.18.051;08.18.071;08.18.101;44.33.020

Notes


Authority
AS 08.01.080 AS 08.18.021 AS 08.18.051 AS 08.18.071 AS 08.18.101 AS 44.33.020
History
Eff. 7/2/77, Register 62; am 4/3/88, Register 105; am 1/22/2004, Register 169