Alaska Administrative Code (Last Updated: January 12, 2017) |
Title 17. Transportation and Public Facilities. |
Chapter 17.10. Engineering: Encroachments, Driveways, and Road Approaches. |
Article 17.10.2. Driveway and Approach Road Permits. |
Section 17.10.080. Permit issuance.
Latest version.
-
(a) The department will, in its discretion, issue a permit for a driveway or approach road that does not require a traffic impact analysis under 17 AAC 10.060(c) upon the payment of the $500 performance deposit required under 17 AAC 10.065 by an applicant. (b) The department will issue a permit for a driveway or approach road that requires a traffic impact analysis under 17 AAC 10.060(c) when the applicant has performed the mitigation in a manner acceptable to the department under 17 AAC 10.070.
Authorities
19.05.020;19.05.040;19.30.051;19.30.121;19.40.065;44.42.030
Notes
Authority
AS 19.05.020 AS 19.05.040 AS 19.30.051 AS 19.30.121 AS 19.40.065 AS 44.42.030History
Eff. 5/4/2000, Register 154