  • An underground facility crossing of a runway must be installed by boring, coring, or jacking under the runway surface. Wet-boring is prohibited. The department may allow trenched or open-cut construction where untrenched construction is not practical. An underground facility crossing in a department right-of-way must conform to the specifications set out in any special provisions of the utility permit.  
    

Authorities

02.15.020;02.15.102;02.15.106;44.42.020;44.42.030

Notes


Reference

17 AAC 15.012
Authority
AS 02.15.020 AS 02.15.102 AS 02.15.106 AS 44.42.020 AS 44.42.030
History
Eff. 7/15/2009, Register 191