Section 18.15.020. Permit applications.  


Latest version.
  • 	(a)  Except as provided in 18 AAC 15.130 - 18 AAC 15.140, an applicant for a permit or written approval subject to 18 AAC 15.020 - 18 AAC 15.100 must serve a complete application on the department.  
    	(b)  An applicant must serve a complete application under (a) of this section for the department's review at least  
    		(1) five days before the proposed commencement of the operation, for applications for surface oiling permits;  
    		(2) 30 days before the proposed commencement of construction, installation, modification, or improvement, for applications for plan approvals or permits for a sewerage system treatment works, or public water system;  
    		(3)  60 days before the proposed commencement of construction, installation, modification, or improvement, for applications for plan approvals or permits for a municipal sewerage system, treatment works, or public water system project that involves state or federal monetary assistance;  
    		(4) 60 days before the proposed commencement of the operation, for an application for a solid waste disposal permit, short-term variance form water quality standards, or wastewater disposal permit; and   
    		(5) 100 days before the proposed commencement of a pesticide use that requires a permit under 18 AAC 90.  
    

Authorities

46.03.020;46.03.100;46.03.110;46.03.320;46.03.330;46.03.720;46.03.730

Notes


Authority
AS 46.03.020 AS 46.03.100 AS 46.03.110 AS 46.03.320 AS 46.03.330 AS 46.03.720 AS 46.03.730
History
Eff. 11/25/77, Register 64; am 1/7/87, Register 100; am 8/2/90, Register 115; am 2/15/98, Register 145; am 7/11/2002, Register 163; am 4/10/2010, Register 194