Section 18.75.456. Department decision on nontank vessel streamlined oil discharge prevention and contingency plans.  


Latest version.
  • 	(a)  The department will make a decision on a nontank vessel streamlined oil discharge prevention and contingency plan or plan amendment not later than five working days after receipt of a complete application. The department will approve a nontank vessel streamlined plan application submitted under 18 AAC 75.421 if the plan meets the following requirements:  
    		(1) the information submitted conforms to the requirements of 18 AAC 75.426;  
    		(2) any nontank vessel cleanup contractor identified under 18 AAC 75.426(11) is registered under 18 AAC 75.500 - 18 AAC 75.580 for the appropriate vessel fuel classification and region of operation identified in the application;  
    		(3) any nontank vessel incident management team identified under 18 AAC 75.426(11) is registered under 18 AAC 75.500 - 18 AAC 75.580 for the appropriate vessel fuel classification and region of operation identified in the application;  
    		(4) any response planning facilitator identified under 18 AAC 75.426(14) is registered under 18 AAC 75.500 - 18 AAC 75.580 to provide the appropriate response planning facilitation services identified in the application.  
    	(b)  A nontank vessel plan is effective for  
    		(1) five years after the date the plan is approved by the department; or  
    		(2) a time period shorter than five years, as specified in the department's approval letter.  
    	(c)  Nontank vessel plans are available for review as public records upon request to the department.   
    

Authorities

46.03.020;46.04.030;46.04.055;46.04.070

Notes


Authority
AS 46.03.020 AS 46.04.030 AS 46.04.055 AS 46.04.070
History
Eff. 11/27/2002, Register 164; am 9/4/2014, Register 211; am 4/16/2016, Register 218