Section 2.12.933. General design-build requirements.  


Latest version.
  • 	(a)  The procurement officer may conduct a design-build procurement process only if the commissioner of transportation and public facilities determines in writing that it is advantageous to the state.  
    	(b)  When a design-build procurement process is used, the request for proposals must solicit a single price for both design and construction services. Nothing in this subsection prohibits a multi-step award process.  
    	(c)  The provisions of 2 AAC 12.931 - 2 AAC 12.949 apply to, and are incorporated in, all design-build construction contracts entered by an agency.  
    	(d)  Design-build construction contracts must be procured  
    		(1) in accordance with AS 36.30.200 - 36.30.265; and  
    		(2) except as provided in 2 AAC 12.931 - 2 AAC 12.949, in accordance with 2 AAC 12.220 - 2 AAC 12.315 (Competitive Sealed Proposals); in the case of inconsistency with 2 AAC 12.220 - 2 AAC 12.315, the provisions of 2 AAC 12.931 - 2 AAC 12.949 control.  
    

Authorities

36.30.040;36.30.200

Notes


Authority
AS 36.30.040 AS 36.30.200
History
Eff. 8/21/2005, Register 175