Section 20.25.225. Potential of gas wells.
Latest version.
-
All gas wells must be tested by a multi-point back-pressure method before regular production. The commission will approve alternative test methods if the commission determines that they provide substantially the same information as the multi-point back-pressure method. The test results and calculations must be reported to the commission on the Gas Well Open Flow Potential Test Report (Form 10-421) within 30 days after the test.