Section 20.40.270. Release of grant payments.


Latest version.
  • 	(a)  The authority may withhold payment under an authority grant until the grantee provides any documentation or other confirmation requested by the authority of information and statements submitted by the grantee either in the grant application or otherwise in support of the grant or implementation of the grant.  
    	(b)  With the prior approval of the board, the authority may retain a stated amount from an authority grant to pay the authority's out-of-pocket administrative costs incurred in connection with the grant.  
    

Authorities

37.14.045;47.30.031;47.30.051;47.30.056

Notes


Authority
AS 37.14.045 AS 47.30.031 AS 47.30.051 AS 47.30.056
________________________
History
Eff. 10/24/2004, Register 172; am 5/11/2012, Register 202