Section 3.107.685. Project operations and maintenance reporting.  


Latest version.
  • For a project constructed with a renewable energy grant, the grantee shall provide to the authority reports on project operations and maintenance for the periods and with the information that the authority specifies in the grant agreement. The authority may require information on project operations and maintenance activities and cost, other costs of the project, energy output, estimated fuel displacement resulting from the energy output, discussion of operational issues, and other information useful to the authority for its evaluation of the project and the grant. If the grantee fails to provide information as required under this section and in the grant agreement, the authority may determine the grantee ineligible for recommendations for future renewable energy grants or ineligible for other future grants from the authority.   
    

Authorities

42.45.045;44.83.080

Notes


Authority
AS 42.45.045 AS 44.83.080
History
Eff. 10/16/2009, Register 192