Section 3.52.630. Standards for nonfuel costs.  


Latest version.
  • Nonfuel costs used in the calculation of power cost equalization per kilowatt-hour are subject to the following standards:  
    		(1) depreciation rates must be in accordance with the guidelines established by the Rural Electrification Administration that were in effect as of January 1, 1988, or, if different, the standards established by the commission;  
    		(2) depreciation expense is not allowed on plant funded with grants, contributions in aid of construction, or other nonutility money; and  
    		(3) unless the commission authorizes a different method of cost recovery appropriate to the overhaul, costs for major overhauls on equipment must be amortized over an appropriate period approved by the commission.  
    

Authorities

42.05.141;42.05.151;42.45.110;42.45.130;42.45.160;42.45.170

Notes


Reference

3 AAC 52.610
Authority
AS 42.05.141 AS 42.05.151 AS 42.45.110 AS 42.45.130 AS 42.45.160 AS 42.45.170
History
Eff. 10/28/89, Register 112; am 9/11/2004, Register 171