Section 5.40.160. Acceptance determination.  


Latest version.
  • 	(a)  The PNP coordinator shall review a submitted application for completeness and determine whether it includes the completed management feasibility analysis described in 5 AAC 40.130(b). If the PNP coordinator determines that the application form is not complete or does not contain a completed management feasibility analysis, the PNP coordinator shall request, in writing, the necessary information from the applicant to complete the application. An application will not be accepted until the PNP coordinator determines that the application is complete and that it contains a completed management feasibility analysis.  
    	(b)  The 60-day time period for processing an application under 5 AAC 40.190, Schedule A, will begin when the application is accepted under this section.  
    

Authorities

16.05.020;16.05.092;16.10.400

Notes


Authority
AS 16.05.020 AS 16.05.092 AS 16.10.400
History
Eff. 3/31/85, Register 93; am 4/28/95, Register 134