Section 8.80.120. Authorization for alterations or welded repair.


Latest version.
  • Alterations or welded repair on boilers and unfired pressure vessels must be performed  
    		(1) under the direct supervision of a special or deputy inspector; or  
    		(2) by a person in possession of a repair stamp issued by the NB, if that person  
    			(A) submits a written quality-assurance system for acceptance by the chief inspector; to be accepted, the quality-assurance system must detail the personnel responsibilities and operating procedures for performing welded repair in accordance with the ASME Code or as defined in the NBIC;  
    			(B) has available a copy of Section IX of the ASME Code, the sections of the ASME Code that are applicable to the vessel being worked on, and the NBIC; and  
    			(C) has submitted a tracer number request form and received a tracer number from the department's Anchorage office.  
    

Authorities

18.60.180;18.60.315

Notes


Authority
AS 18.60.180 AS 18.60.315 Editor's note: The tracer number request form prescribed in 8 AAC 80.120(2) is available by contacting the Department of Labor and Workforce Development, Mechanical Inspection Section, P.O. Box 107020, Anchorage, Alaska, 99510-7020, or by calling (907) 269-4925.
________________________
History
Eff. 6/21/84, Register 90; am 10/21/92, Register 124; am 12/17/99, Register 152; am 11/1/2000, Register 156

References

8.80.120