Section 3.50.810. Disputes.  


Latest version.
  • 	(a)  Disputes regarding implementation of 3 AAC 50.750 - 3 AAC 50.820 must be filed with the commission for consideration under the complaints procedures prescribed in 3 AAC 48.120 - 3 AAC 48.130.  
    	(b)  If a dispute arises under this section, an electric utility shall submit to the commission the cost justification necessary to support the methodology and calculations used in developing interconnection charges under 3 AAC 50.760, integration fees and payments under 3 AAC 50.765, purchase rates under 3 AAC 50.770, and sale rates under 3 AAC 50.780, to the extent relevant to resolving the complaint. The commission may review the data submitted by an electric utility under this subsection. The electric utility has the burden of providing justification for its data.  
    	(c)  A claim by an electric utility that a period under 3 AAC 50.770(b)(1) has occurred or will occur is subject to verification by the commission either before or after the occurrence, upon the commission's own motion or upon complaint by a qualifying facility.  
    

Authorities

42.05.141;42.05.151

Notes


Authority
AS 42.05.141 AS 42.05.151
History
Eff. 11/20/82, Register 84; am 3/11/2016, Register 217